Sidemount Railing Post Installation
Install Viewrail Signature Cable Railing sidemount posts with this step-by-step guide. Use it for post layout, pilot drilling, fastening, leveling, and final post setup on a non-compressible mounting surface.
Watch installation videos on our YouTube channel: youtube.com/viewrail
Tools for Signature Cable Railing sidemount post installation
Post Level (Provided)
Tape Measure
Pencil
Drill
3/16", 1/4", and 3/8" Drill Bits
Dead Blow Hammer
Before you install sidemount cable railing posts
Review your project materials to identify each post type.
If you are installing rod posts, insert the foam blocks before you begin.
Mount posts only to a non-compressible surface. Do not mount to drywall or carpet.
Systems installed near the coast include isolator components and do not use foam inserts.
Consult the POST ORDER OF INSTALLATION page to see which order your posts should be installed
Installing Side Mount Cable Railing Posts

Refer to your layout drawing to find the mounting location for each post.
Side-mounted posts are designed with the top of the plate mounted
1 3/8"below the finished floor surface.Mark your top line before drilling.
If you are mounting to a skirtboard or stair fascia, place the posts to maintain a
36"handrail height.

Place the posts and mark the holes for pilot drilling.
Have a second person hold the post while you mark the holes.

If you are using lag screws, drill pilot holes with a
3/16"bit.Drill
4 1/4"deep holes for the5"lag screws.If you are using through bolts, drill the fastener holes completely through the double
2xmaterial.

Slide the foam insert into each post.
This keeps the rods from rattling.
Note: Systems installed near the coast include isolator components and do not need foam inserts.

Mount the post with 4 washers and screws.
Make sure the post sits snug against the fascia.

Insert the
6"carriage bolt through the sidemount plate and predrilled holes.Each set of bolts passes through a
2" x 6"steel backing plate.Add the washer, then the lock washer, then the nut.
Tighten the nuts evenly and firmly.

Once the post is snug, use the post level to confirm it is level.
Use the post level again to confirm the post is plumb.
If the post is not fully level or plumb, adjust it with shims.
Once the post is firmly mounted, break off any excess shim material.

Use a dead blow hammer to tap the end cap into the bottom of each post.
Next steps
After your sidemount posts are installed, continue with:
Get Help from Us
Is this not the product you're looking for? Troubleshoot your issue by contacting our customer service team. 866-432-0541 or customerservice@viewrail.com
Last updated
Was this helpful?