# Vedera Installation

<figure><img src="/files/AodsB7wkLgmk6blDlfI9" alt=""><figcaption></figcaption></figure>

### <mark style="color:blue;">Tools Needed for This Installation</mark>

<figure><img src="/files/qH4NtXxHCU1OwWKYuQkk" alt=""><figcaption></figcaption></figure>

### <mark style="color:blue;">Things to Know Before You Get Started</mark>

{% columns %}
{% column %}
• Read over the provided material prior to the start of your installation
{% endcolumn %}

{% column %}

<figure><img src="/files/ilv0G5qbFcYcgnC5O5BI" alt=""><figcaption></figcaption></figure>
{% endcolumn %}
{% endcolumns %}

***

### <mark style="color:blue;">Vedera Tread Installation Steps</mark>

{% columns %}
{% column %}
![](/files/2vKchzGj3TgYT5MDT2yI)

• Once your FLIGHT treads are installed, count the&#x20;predrilled standoff pin hanger bolts and prepare the&#x20;correct amount of pin hardware
{% endcolumn %}

{% column %}
![](/files/wus1eBxN9h40Vd1lIqcR)

• Thread a Glass Stud over each hanger bolt until the stud&#x20;is flush against the tread
{% endcolumn %}
{% endcolumns %}

{% columns %}
{% column %}
![](/files/31gQjqqqy6noIWtmuYpP)

• Slide a plastic bushing over each Glass Stud\
• At this point, read the rest of the instructions & prep&#x20;the remaining hardware for the first panel you will&#x20;be installing\
• This will shorten the amount of time manually holding&#x20;the panel in place
{% endcolumn %}

{% column %}
![](/files/vSRYrCJf0UuKSUTTAkKE)

• Refer to the engineering prints provided to you to&#x20;identify the first panel\
• With the help of a partner, use Glass Suction Cup&#x20;Handles to position the 1st glass panel into place\
• Slide the holes in the panel over each gasket and hold&#x20;this in place while the remaining hardware is mounted
{% endcolumn %}
{% endcolumns %}

{% columns %}
{% column width="50%" %}
![](/files/t7mqKCSYcKxXvHWyloUU)

• While your partner holds the glass in place, slide the&#x20;Vedera Shim then the Metal Clamp Plate over each of&#x20;the hanger bolts as shown
{% endcolumn %}

{% column width="50%" %}
![](/files/tWEO14VmXtsZZr8AS7hi)

• Slide a Vedera Pin on to each of the hanger bolts\
• Continue to hold the panel in place as the fastening&#x20;mechanism is applied in the following step
{% endcolumn %}
{% endcolumns %}

{% columns %}
{% column %}
![](/files/roYBKP0Tjqk2KXJG0GPK)

• Hand tighten a nut on to each hanger bolt\
• There will be play in the exact positioning of the glass&#x20;panel, this will allow you to make adjustments in Step 10
{% endcolumn %}

{% column %}
![](/files/pGMUMtYGJrA2nroAPtEf)

• Using a torque wrench and a 9/16" socket head, tighten&#x20;the first and last nut on the Vedera Pin to 23 lb ft\
• This will make it easier if you need to readjust the fitment&#x20;once all the other glass panels are installed

Repeat **STEPS 1-8** for each panel on\
your run
{% endcolumn %}
{% endcolumns %}

{% columns %}
{% column %}
![](/files/rkdYfNqrJKWZjmwc5kN5)

• Once all the panels are in place, ensure that each is&#x20;aligned with it’s neighbors\
• There will be a 1" gap between panels
{% endcolumn %}

{% column %}
![](/files/eXZo0mSJ5MHx6DNLIwRh)

• Using a torque wrench and a 9/16" socket head, tighten&#x20;all the remaining nuts on the Vedera Pins to 23 lb ft
{% endcolumn %}
{% endcolumns %}

{% columns %}
{% column %}
![](/files/3Ap6oIbfgsKdAh9JxktF)

• Identify and prepare the Vedera wood covers\
• Although the rubber O rings will provide a snug fit in the&#x20;predrilled holes for the wood covers, it is recommended&#x20;to use silicone on the face of the pin around the bolt&#x20;hole in order to provide additional strength\
• Apply a line of silicone around each O ring\
• Attach the wood covers onto each pin\
• These will fit snugly and could require soft taps to place
{% endcolumn %}

{% column %}
![](/files/ccv0E1WgUcmuswWyxEjO)

*<mark style="color:blue;">If your FLIGHT system has a platform and there are at least&#x20;two long Vedera Caps that meet at a corner, they will come&#x20;to you with an extra few inches of cap. This is so you can dry&#x20;fit them and cut on site for the best look possible.</mark>*
{% endcolumn %}
{% endcolumns %}

***

### Get Help from Us

Is this not the product you're looking for? Troubleshoot your issue by contacting our customer service team. [866-432-0541](tel:8664320541) or <customerservice@viewrail.com>


---

# Agent Instructions: Querying This Documentation

If you need additional information that is not directly available in this page, you can query the documentation dynamically by asking a question.

Perform an HTTP GET request on the current page URL with the `ask` query parameter:

```
GET https://resources.viewrail.com/install/glass-railing/vedera-installation.md?ask=<question>
```

The question should be specific, self-contained, and written in natural language.
The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.